Governor Gianforte Supporting 4.7% Flat Income Tax for Montana Taxpayers      Fort Peck Tribal Executive Board Approves $175 Per-Capita Payment      Suspected members of an interstate drug ring make their initial appearance in federal court      Bridger Pipeline Hosting Public Meetings on Proposed Oil Pipeline      MTN Sports High School Football Rankings      Sports Broadcasts This Week      Interested in Becoming a Montana Highway Patrol Trooper?      Trump signs bill to continue water pipeline projects in northeastern Montana      Where air conditioning is most — and least — common in Montana      Federal Emergency Management Agency Designates the Fort Peck Indian Reservation and Off-Reservation Trust Land as Natural Disaster Areas Due to Severe Winter Storms and Straight-Line Winds      Montana Board of Public Education Revokes Teaching License of Former Scobey Teacher      Valley County Sees Slight Population Loss From Migration       Scotties Fall To Fairfield      Friday Night Scoreboard      Scottie Volleyball Handles Poplar      Saturday Sports Scores      DCI investigating officer-involved critical incident in Harlem      AAA Weekly Report on Gasoline and Diesel Fuel Prices      Latest Drought Monitor      Arrests Made in Polar After Over a Pound of Suspected Methamphetamine Discovered During Traffic Stop      Man Arrested After Driving Through Front Entrance of Reynolds       Voter Registration Reminder and Ballot Certification      Channing Eder Arrested      Scottie Cross Country Competes At Frazer Invitational      Diesel prices shoot upward as top farm-state GOP senator begs Trump for export embargo      
News
News
 Sep 30, 2026

Bridger Pipeline Hosting Public Meetings on Proposed Oil Pipeline

Bridger Pipeline LLC is hosting two open public meetings to share details about its proposed 36-inch diameter steel heavy crude oil pipeline project in Montana, conducted as part of the Montana Major Facility Siting Act application process. Both sessions will present the same information.
 
Key Topics & Objectives:
Project Details & Need: Explanation of why the expansion is needed and presentation of maps showcasing the proposed route and alternatives.
 
Public Input & Community Feedback: Bridger seeks community input on potential impacts—including land use, local economy, natural resources, social factors, and taxation—as well as concerns from nearby landowners and residents.
 
Q&A and Submissions: Attendees can ask questions directly and submit written comments in person or via QR code.
 
Note: Meeting materials will be available online after October 9th, 2026.
 
Meeting 1:
Wednesday, October 7th, 2026
5:00 PM – 7:00 PM
Location: Cottonwood Inn and Suites, 54250 US-2, Glasgow, MT 59230
 
Meeting 2: Thursday, October 8th, 2026 | 5:00 PM – 7:00 PM
Location: Fallon County Fairgrounds, 3440 MT-7, Baker, MT 59313
 
The proposed Bridger Pipeline Expansion would transport crude oil from the existing Keystone XL Canadian Segment in Alberta, Canada to a proposed 647-mile pipeline traveling through parts of Northern and Eastern Montana and Eastern Wyoming. Though there are similarities to the cancelled US segment of the Keystone XL pipeline, the project proposed a different route. If constructed, the project would transport up to 550,000 barrels of crude oil per day.
 
  • Origin: U.S.–Canada border in Phillips County, Montana, connecting to the proposed Prairie Connector pipeline.
  • Terminus: Guernsey crude oil terminal hub in Guernsey, Wyoming.
  • Montana Counties Crossed: Phillips, Valley, Daniels, Sheridan, Roosevelt, Richland, Wibaux, Fallon, and Carter.

Pipeline Details

  • Miles

    646.8

  • Diameter (inches)

    36

  • Additional Capacity

    550,000 bpd

  • Anticipated Construction Start Date

    2027-07-01

  • Year In Service or Expected Completion Year

    2030

  • Cost

    $2 billion