Fort Peck Northwest project to pause for winter Work on MT 24 will resume spring 2027.      Boy Scout Troop Selling Fresh-Cut Christmas Trees      All Are Welcome to Community Thanksgiving Day Dinner       Realignment for Eastern C and Northern B in 2027/2028 School Year      Thanksgiving Dinner Costs Rise 6% Nationwide in 2026—and Even Higher in Montana      Montana Winter Outlook      Holiday 3 on 3 Basketball Tournament Scheduled for December 31st at GHS      James Fauth Graduates from Montana Law Enforcement Academy       Trump's plan sparked anger, but beef imports had already been rising as US cattle numbers fell      Glasgow Scottie Wrestling      Glasgow Ice Dawg Results      Montana One of 29 States that Cap Insulin Co-Pays at $35      Valley County Cannibas Sales Total $159,898 in October      Bobcats Defeat Grizzlies for Big Sky Conference Title      Christmas Stroll Next Weekend in Glasgow      Sports Broadcasts This Week      Flint Creek and Grass Range-Winnett Claim State Football Titles      High School Football Playoffs      Men’s Basketball League Scores      Block of Bucks Collection On Friday      2027 Legislative Committee Assignments      Montana Unemployment Rate 3.1%      Montana’s midterm election turnout rate held steady, while county results varied widely      Valley County School Districts Trail Roosevelt County Neighbors by Over 11-to-1 in Oil and Natural Gas Tax Payouts      Sen. Windy Boy faces ethics investigation, renewed calls to resign      
News
 Nov 27, 2026

Fort Peck Northwest project to pause for winter Work on MT 24 will resume spring 2027.

 

FORT PECK, Mont. — The Montana Department of Transportation (MDT) and Riverside Contracting Inc. announce an updated paving schedule for the Fort Peck Northwest project on Montana Highway 24 (MT 24). To promote long-term roadway performance and durability, sections totaling approximately 3.5 miles will be left as a treated gravel surface this winter. These sections will be paved during the spring of 2027.

 

Recent fall precipitation has increased moisture levels in the underlying soils, requiring additional work to strengthen the roadway foundation before paving can begin. This fall, crews blended cement into the gravel base to improve stability.

 

Motorists should expect gravel roadway sections and reduced speed limits throughout the project area during the winter months. Riverside Contracting Inc. will continue working with MDT to maintain these sections and provide the smoothest and safest driving conditions possible until paving activities resume. For the most up-to-date information regarding road conditions, please visit 511mt.net.

 

The public is encouraged to contact Glendive District Project Delivery Engineer Jay Fleming by calling 406-345-8209 or emailing jfleming@mt.gov with questions or comments about the project. Km